(In this YAWS version a few editorial alterations have been made to the description of the CPR and Practice Directions, eg references to Part 3.8 have been changed to Rule 3.8, to ensure consistency with the remainder of the site.)
| This Report is referred to in: Ashton v Securum Finance [32], UCB v Halifax [10], [12]. |
IN THE COURT OF APPEAL (CIVIL DIVISION)
ON APPEAL FROM THE QUEEN'S BENCH DIVISION
(MR JUSTICE POPPLEWELL )
Royal Courts of Justice,
Strand,
London WC2
Monday 30th November 1998
Before:
MR JUSTICE KAY
- v -
MANZUR MALIK
Defendant/Respondent
(Computer Aided Transcript of the Stenograph Notes of
Smith Bernal Reporting Limited, 180 Fleet Street,
London EC4 A 2HD
Tel: 0171 421 4040
Official Shorthand Writers to the Court)
MR P LAWRENCE (Instructed by Messrs Boyd & Hutchinson, The Exchange, 136 Streatham High Street, London SW16 1BW) appeared on behalf of the Applicant
The Respondent did not appear and was not represented
(As approved by the Court )
©Crown Copyright
Monday 30th November 1998
JUDGMENT
| 1. | MR JUSTICE KAY: On 24th April 1998 Deputy Master Chism ordered that the plaintiff's action be dismissed for want of prosecution. Her appeal against that decision was dismissed by Popplewell J on 5th June 1998. She now renews her application for leave to appeal against the decision of Popplewell J. | ||
| 2. | The action arises out of a gas explosion at a grocer's shop in Tooting owned by the defendant, which occurred on 21st August 1987. The plaintiff's husband was killed in the explosion, as were others. A letter before action was written promptly on 28th April 1988, but no writ was issued until 5th April 1990. There were difficulties over service, and service was not effected until September 1990. On 9th October 1990 the defendant filed a defence. There being no reply, proceedings were deemed to be closed 14 days thereafter and, since this was a case to which order 25 rule 8 applied, automatic directions under that rule became effective from that date. Those automatic directions imposed obligations on the plaintiff as to discovery, disclosure of evidence and setting down. | ||
| 3. | Popplewell J accepted an assurance from counsel that setting down had to be within fifteen months. It is not clear where that figure came from, as the period specified within the rule is six months. In any event, the plaintiff did not comply with any of the directions and no further step was taken in the proceedings until 19th April 1993. Thereafter it is unnecessary to recount in detail the lack of progress of the action. On three separate occasions the plaintiff's solicitors were obliged to serve notice of an intention to proceed, notwithstanding that over a year had gone by since the last step was taken. Eventually, in 1994, the matter came before the court for further directions to be made and a new timetable was set out by the Master on that occasion. That timetable provided for setting down within a further three months. None of the requirements of that timetable were observed by the plaintiff or, indeed, by the defendant. The result was that by the time 1998 had come round the matter still had not been set down. | ||
| 4. |
Eventually the plaintiff's solicitors set the case down for hearing.
Not surprisingly, the defendant then sought to strike the matter out
for want of prosecution. When the matter came before the Deputy Master,
he concluded that there had been inordinate and inexcusable delay and
that prejudice was likely to result for the defendant from that delay.
When the matter came on appeal before Popplewell J, the matter was put
on the same basis as it had been before the Deputy Master and also on a
second basis, that in the light of recent decisions of the Court of
Appeal in | ||
| 5. | Having reviewed the authorities, he came to the following conclusions: | ||
| |||
| 6. | The judge therefore concluded that this case did amount to an abuse of process and rejected the appeal on a different basis from the Deputy Master. | ||
| 7. |
In | ||
| |||
| 8. |
Pill LJ said | ||
| |||
| 9. |
In that case there had been orders, including directions as to setting
down, made at a time when the defendant was seeking to strike out the
claim, and those orders had not been complied with. There can be no
doubt that the court attached great weight to this fact. For example,
Pill LJ said | ||
| |||
| 10. |
It was this fact which enabled the court to conclude, as Pill LJ put
it, that | ||
| |||
| 11. | which, it was observed, had been acknowledged in the solicitor's affidavit. | ||
| 12. | On behalf of the applicant in this case, it is argued by Mr Patrick Lawrence in his helpful skeleton that Popplewell J found nothing in this case that took it out of the ordinary. It was, as he puts it: | ||
| |||
| 13. | Hence, he argues, it cannot come within the principles recognised by the authorities. | ||
| 14. |
For my part, there are aspects of the delay in this case which put it
at the top end of the cases of delay with which the court is concerned,
and I have considerable sympathy with the views taken by Popplwell J.
However, I am troubled by the fact that he nowhere addresses the issue
of whether the delay was with the "full awareness of the consequences",
which Nourse J and the other members of the court in | ||
| 15. |
The fact that the court in | ||
| 16. | LORD JUSTICE ROBERT WALKER: I agree. | ||
| ORDER: Application granted, with costs in the appeal. |