| 1. |
Following the outcome
of trials of the principal issues the first defendant (SCL) has sought orders
pursuant to Section 51 of the Supreme Court Act 1981ActsActs against the second claimant,
Mr David Flood (Mr Flood), and has also joined the former solicitors who once
acted for the first claimant (FOQ), Winward Fearon (WF) to obtain a similar
order against them. (Mr Flood and his brothers are directors of FOQ but Mr
Flood runs the company and its affairs.) In March 1999 I decided that FOQ
was entitled to £214,793.87 and that SCL's contested counterclaims failed.
In December 1999 I rejected FOQ's claim under section 2(2) of the Misrepresentation
Act 1967. SCL had paid £350,000 into court on 24 March 1995 so I then decided
that, whilst FOQ was entitled to its costs to that date, SCL was entitled
to recover its costs from FOQ thereafter. (FOQ was also awarded interest of
nearly £50,000 so that the total for which judgment was given was £264,462.99;
that amount was to be treated as an interim payment on account of SCL's costs
after 24 March 1995.)
| 2. |
FOQ has had no money
for a long time and never had much before the inception of this action. SCL
was aware of FOQ's position and has long been curious (and concerned) to know
how and by whom this action has been financed. Its case, in essence, is that
SCL although faced with a grossly inflated claim, acted in an appropriate
manner at a very early stage of the litigation by paying into court what has
been proved to be a generous amount and which ought to have been regarded
as generous at that time. It was therefore submitted that those who decided
to press on with this litigation in the expectation that a greater sum would
be recovered should be required to compensate SCL as that expectation not
only did not materialise but was never likely to do so.
| 3. |
Similarly but for
different reasons Mr Flood has long been concerned about SCL which ceased
operations at the outset of the sub-contract. The costs of its defence was
met from group funds, specifically by Morrison Construction Limited. Mr Colin
Reese QC submitted that there was nothing in this point since Mr Flood or
Winward Fearon have been aware of the reality since 1995 (at latest) and a
formal undertaking was given willingly at their request that Morrison Construction
Limited would meet any judgment in favour of SCL.
| 4. |
The issues which
I have now to determine are agreed and are the following:
| | |
| 1 |
Did
the second claimant, Mr David Flood, fund and/or maintain and/or finance the
proceedings, or any part thereof, brought by the first claimant against the
defendants?
| 2 |
Is
it just in all the circumstances to make Mr David Flood pay the unrecovered
costs (or a proportion thereof or a fixed lump sum representing a part of
the unrecovered costs) of the proceedings?
| 3 |
Does
the court have jurisdiction to make an order against Winward Fearon? Did the
second Part 20 defendant, Winward Fearon, fund and/or maintain and/or finance
the proceedings or any part thereof, brought by the first claimant against
the defendants?
| 4 |
Is
it just in all the circumstances to make Winward Fearon pay the unrecovered
costs (or a proportion thereof or a fixed lump sum representing a part of
the unrecovered costs) of the proceedings?
| 5 |
To
whom should the insurance monies which were paid into Court pursuant to the
order dated 9 June 2000 be paid?
(The last
issue refers to legal costs insurance which was obtained by FOQ in 1997 and
1998.)
| | | | |
| 5. |
Before I set out
the facts I need to refer to the first part of issue 3. WF maintain that as
a matter of law I do not have power to make an order against it. Mr Nigel
Davis QC and Mr Edmund Cullen submitted that the only power was to be found
in sections 51(3). Section 51 of the 1981 Act, as amended by the 1990 Act,
is, in material parts, in these terms:
| | |
| "(1) |
Subject
to the provisions of this or any other enactment and to rules of court, the
costs of and incidental to all proceedings in (a) the civil division of the
Court of Appeal; (b) the High Court; and (c) any county court, shall be in
the discretion of the court.
.....
| (3) |
The
court shall have full power to determine by whom and to what extent the costs
are to be paid.
....
| (6) |
In
any proceedings mentioned in subsection (1), the court may disallow, or (as
the case may be) order the legal or other representative concerned to meet,
the whole of any wasted costs or such part of them as may be determined in
accordance with rules of court.
| (7) |
In
subsection (6), wasted costs means any costs incurred by a party (a) as a
result of any improper, unreasonable or negligent act or omission on the part
of any legal or other representative or any employee of such a representative;
or which, in the light of any such act or omission occurring after they were
incurred, the court considers it is unreasonable to expect that party to pay.
"
| | | |
| 6. |
Mr Davis for WF
submitted that no order could be made under section 51(6) or (7) in the absence
of improper, unreasonable or negligent conduct. He also submitted there was
authority binding on me that no order could be made under section 51(1) and
(3) against the legal representative of a party. In Tolstoy-Miloslavsky v Aldington[ [1996] 1 WLR 736] the Court of Appeal held that there was no jurisdiction
under s 51(1) and (3) of the 1981 Act to make an order for costs against legal
representatives when acting as legal representatives. There were only three
categories of conduct which could give rise to an order for costs against
a solicitor: (i) if it was within the wasted costs jurisdiction of section
51(6) and (7); (ii) if it was otherwise a breach of duty to the court such
as could found an order (e.g. if he acted, even unwittingly, without authority
or in breach of an undertaking); and (iii) if he acted outside the role of
solicitor (e.g. in a private capacity or as a third party funder for someone
else). Accordingly it set aside an order in favour of the defendant which
had been made on that basis (although the decision was upheld as a proper
application of section 51(6) and (7)). Rose LJ said at page 745H:
| | |
| |
"There
are only three categories of conduct which can give rise to an order for costs
against a solicitor: (i) if it is within the wasted costs jurisdiction of
section 51(6) and (7); (ii) if it is otherwise a breach of duty to the court
such as, even before the Judicature Acts, could found an order, e.g., if he
acts, even unwittingly, without authority or in breach of an undertaking;
(iii) if he acts outside the role of solicitor, e.g. in a private capacity
or as a true third party funder for someone else.
| | |
There
is, in my judgment, no jurisdiction to make an order for costs against a solicitor
solely on the ground that he acted without fee. It is in the public interest,
and it has always been recognised that it is proper, for counsel and solicitors
to act without fee. The access to justice which this can provide, for example
in cases outwith the scope of Legal Aid, confers a benefit on the public.
Section 58 of the [Courts and Legal Services Act 1990], which legitimises
conditional fees, inferentially demonstrates Parliament's recognition of this
principle. For it would be very curious if a legal representative on a contingent
fee and, therefore, with a financial interest in the outcome of litigation,
could resist an order for costs against himself but one acting for no fee
could not. Whether a solicitor is acting for remuneration or not does not
alter the existence or nature of his duty to his client and the court, or
affect the absence of any duty to protect the opposing party in litigation
from exposure to the expense of a hopeless claim."
|
| | |
This decision
was considered in Hodgson v Imperial Tobacco Ltd[ [1998] 1 WLR 1056]. Lord Woolf
MR, in giving the judgment of the court, said at page 1066C:
| | |
| |
"The
second area of additional jurisdiction is that which arises under the general
jurisdiction of the court as to costs contained in s 51(1) and (3) of the
1981 Act. This is a jurisdiction which cannot arise where a legal representative
is acting only in that capacity in the context of legal proceedings.
There
are therefore three possible heads of jurisdiction under which a legal representative
may be made liable for costs. That this is the position was made clear by
the decision of this court in Count Tolstoy-Miloslavsky v Lord Aldington[ [1996]
1 WLR 736]."
|
| 7. |
Mr Colin Reese QC
for SCL accepted the effect of these decisions but reserved the position of
SCL in the event that they had to be considered by the House of Lords. He
made certain submissions directed to removing SCL from the ambit of Tolstoy-Miloslavsky
but in my judgment it would serve no useful purpose to deal with them as they
do not bring SCL within any of the exceptions. Nevertheless I shall return
to the submission that an order should be made against WF. Otherwise I am
bound to answer the first part of question 3: No.
| 8. |
Mr Christopher Gibson
QC for Mr David Flood accepted that the Court had jurisdiction under section
51 but submitted that the necessary facts had not been made out: Aiden Shipping Ltd v Interbulk Ltd[ [1986] 1 AC 965]. His case in essence is that the
facts of this case simply do not justify such an award. It is contended on
his behalf that he did not materially 'fund' or finance the claim, nor did
he improperly maintain the claim.
| 9. |
Before setting out
the facts it is necessary to record that, inevitably, the documents and evidence
were incomplete. Parts of the documents were redacted as they were privileged.
Mr Flood produced a large number of documents at a relatively late stage.
But for them it would have been very difficult to have got any reasonable
picture. Nevertheless there remain areas where I do not have material to make
any findings, and the redacted passages have made me very cautious about expressing
views about the advice given or not given to FOQ and to Mr Flood. The action
was commenced on 10 October 1994 by FOQ which was then represented by Church
& Church. The partner in charge of the case, Mr Timothy Reynolds, had
been advising FOQ since early 1994. He moved to become a partner of Winward
Fearon so WF took over in January 1995. From the outset FOQ had no money to
pay its solicitors. Church & Church's invoices had not been paid, and
as will be seen, WF's bills were not paid. On 2 February 1995 a discussion
took place between Mr Reynolds, Mr Flood and Mr Jones about funding, which
was noted by Mr Reynolds. Mr Flood thought that about £40,000 was due to Church
& Church and that "he was in effect living off VAT refunds. This raised
major issues about future funding of [the] case". Discussion took place about
FOQ's exposure to an application for security for costs and about Mr Flood
obtaining Legal Aid, since, not for the first or last time, Mr Flood had evidently
been looking up the law. The note of the discussion provides early evidence
not only of Mr Flood's thorough knowledge of the law which undoubtedly has
informed all that he has done and not done, but also of his contacts with
other solicitors some of whom have been paid (but the origins of the payments
are still not entirely clear to me). Mr Reynolds recorded that he would "see
whether WF might be prepared to fund a case on any terms", and from his cross-examination
this included the possibility of providing credit until the conclusion of
the case.
| 10. |
On 1 March 1995
I gave directions towards a trial starting in June 1996. On 24 March 1995
SCL paid £350,000 into court in satisfaction of the claims against it. Although
the notice did not cover any counterclaim in reality it did so since much
of FOQ's claim required decisions about the periods within which its work
was to be carried out and completed and whether it was obliged to do certain
work, both of which areas were central to the counterclaim subsequently advanced.
For all practical purposes if FOQ had wished to accept the offer represented
by the payment into court the action would have been disposed of by agreement.
FOQ had been paid £831,225 so in order to beat the payment into court the
total valuation of its works plus its claims would have to be assessed at
a minimum of about £1,182,000. The actual costs that it incurred in performing
the sub-contract came to about £1,115,000, exclusive of any allowance for
overheads and profit. It had however off-loaded a substantial part of the
costs by means of "credit notes". In my judgment Mr Reese was right in submitting
that if the payment in had been accepted FOQ would have been able to recover
all the costs and its costs of the action (taxed) and with a margin of over
£100,000. SCL subsequently applied for security for costs. Mr Flood maintained
that he was not advised about the payment in, and it seems that there was
no formal written advice. However the payment into court had been preceded
by settlement discussions during which FOQ was offered £400,000 in two tranches.
Mr Reynolds agreed that this was a serious offer and that he undertook to
reply to it but the offer was not accepted (nor was it positively declined).
If FOQ had wanted formal advice about the offer I am sure that it would have
been given, even though SCL's defence was not known in any detail. It was
not sought as Mr Flood (and Mr Reynolds) thought that the amount would be
improved. Mr Reynolds said that at the time of the settlement discussions
Mr Flood had been told of his view that the claim was worth between £500,000
- £700,000 although it was not raised in the discussions. This belief evidently
continued until the end of the trial and was the dominant reason for Mr Flood's
pursuit of the defendants and for his legal advisers' decisions to continue
to assist him.
| 11. |
Thus on 19 July
1995 Mr Reynolds sent a memorandum to Mr David Cornes and Mr Richard Winward,
the senior partners of WF, in which he acknowledged that the firm had heavy
costs outstanding, but he thought that FOQ's claim was "worth a considerable
amount more than £350,000 and that if we keep going Shand/Morrison will make
a higher offer" (although not until after the application for security was
heard). He concluded: "I therefore believe a substantial amount of recoverable
costs will in the end be generated. However, at present, it would look as
if we have to finance the case if we are continue, although money may be generated
from the property company in the near future". I accept SCL's case that by
the autumn of 1995 the action could still have been settled on the basis of
the payment in although the margin that existed at the time of the payment
in would have been extinguished by FOQ's costs since that date.
| 12. |
On 10 November 1995
Mr Recorder Blunt QC gave judgment on SCL's application. He decided that FOQ
should provide £75,000 as security for SCL's costs until the conclusion of
the case. (The defendants were unsuccessful in an application to the Court
of Appeal about the amount of the security.) He also dismissed an application
that the action should be struck out on the ground that it was being maintained
by a third party and thus rejected the defendants' case that Mr Flood's funding
of the action amounted to unlawful maintenance. The action was then stayed
since FOQ could not provide the security. Mr Reynolds and Mr Flood returned
from the court and took stock of the case with Mr Winward, who was the finance
partner of WF. Mr Reynolds' note states: "RW made it plain that we could not
go on acting without security and part payment. Left that DCF would review
position and go back to RW early next week." Mr Winward followed up the meeting
by asking Mr Reynolds to prepare a full report together with a list of outstanding
costs (including those due to Church & Church). Mr Winward made it clear
in his evidence that he was not involved in the detail of the case but as
an equity partner and the finance partner he was concerned about the debt
and received reports from Mr Raff, who was responsible for the firm's accounts
and debts.
| 13. |
On 15 November 1995
the defendants' solicitors notified Mr Flood that they would seek an order
for costs against him on the grounds that he was funding the proceedings.
On 4 December 1995 FOQ assigned its causes of action to Mr Flood. The consideration
was £37,800 being the balance of the loans then due to Mr Flood from FOQ which
had been made since September 1993. Mr Flood was then able to obtain Legal
Aid to pursue the claims against SCL. Although that step enabled the claims
against SCL to be maintained and the likely consequences of SCL's proposed
application to be limited (both at least for the time being), it did not however
solve the problem of the fees due from FOQ. As Mr Winward pointed out in a
discussion on 12 January 1996 with Mr Reynolds and Mr Cornes (another equity
partner of WF) if the assignment were successful then WF was left with a right
against a company with no assets even though WF retained the overall conduct
of the case. On 19 January 1996 the application was made formally. The grounds
were, in summary, that Mr Flood knew that FOQ would not be able to pay the
defendants' costs if it lost; that he maintained or funded the action "not
upon the usual commercial terms"; that he stood to gain personally if FOQ
was successful; and that he had managed, conducted and supervised the action.
The defendants opposed an application to substitute Mr Flood for FOQ but on
23 February 1996 His Honour Judge Thornton QC allowed the application. During
1996 WF continued to press for payment of the fees owed by FOQ and sought
a guarantee from Mr Flood but nothing was achieved. On 3 July 1996 Mr Flood
acquired for £5,000 the debts of £22,590 due from FOQ to Church & Church
and reached a similar settlement with Mr Jones about the fees due to him in
1995 and 1996 (i.e. a payment of £6,800 for fees of £37,187) whereby FOQ owed
him a further £60,000. I refer later to Mr Flood's loans. Mr Flood had therefore
another interest in the outcome of the action.
| 14. |
In September 1996
Mr Reynolds moved from WF to become a partner in Constant & Constant.
Mr David Gwillim succeeded him as the partner responsible at WF. (Mr Barry
Rideout was employed by WF from June 1996 to June 1998 to have the day to
day conduct of the case). Before leaving Mr Reynolds recorded that FOQ owed
Church & Church £23,364 (which indicates that Mr Flood's deal with that
firm was apparently then unknown to Mr Reynolds, who still had an interest
in the amount recovered by his former firm). At a consultation on 28 November
Mr John L Powell QC and Mr Andrew Stafford warned Mr Flood that the case was
not ready for a trial in April. Just before Christmas 1996 the Court of Appeal
allowed the appeal from the order of Judge Thornton QC on the grounds that
FOQ had no right under the sub-contract to assign certain claims to Mr Flood
(81 BLR 31). (Other parts of the appeal had been stayed pending the decision
of the House of Lords from the judgment in Norglen Ltd v Reeds Rain Prudential[
[1996] 1 WLR 864].) Thus the main claims in the action could only be maintained
by FOQ. By that time the action was heading for trial dates of 14 April 1997
and 12 January 1998. Mr Flood therefore had to ask WF whether and on what
terms it would be prepared to continue to act for FOQ (assuming the stay was
lifted). On 23 December 1996 Mr Gwillim wrote to Mr Flood:
| | |
| |
"Shand
Construction Limited and Others
| | |
You
have asked me to indicate on what terms Winward Fearon would be prepared to
continue to act for Floods of Queensferry Ltd in these proceedings. I have
discussed the position with Richard Winward and I am pleased to be able to
tell you that we would be happy to represent Flood of Queensferry Ltd up to
the conclusion of the trial of the first part of these proceedings fixed for
April 1997.
| | |
The
preparation for the forthcoming trial requires the application of a range
of resources. That will encompass incurring substantial time costs for my
time and that of Barry Rideout. In addition, there is the probability that
Counsel's fees will also be incurred, witness expenses will have to be met
and charges of expert witnesses will have to be deal with as well. As you
will appreciate, whilst I can take a view and adopt a position in relation
to this firm's costs I am not able to bind my partners to meet fees and expenses
of Expert witnesses and other disbursements such as Counsel.
| | |
Accordingly,
what I propose is that Winward Fearon agrees to represent Floods of Queensferry
Ltd up to the conclusion of the April trial and not to render a Bill of costs
until May 1997 or to press for the payment of the earlier unpaid bills on
the following conditions.
| | |
| 1 |
All
or any proceeds of any settlement with the Defendants are paid to my firm's
client account.
| 2 |
You
undertake full and exclusive responsibility for meeting all disbursements
including Expert's fees and that this firm is absolved from any liability
therefor.
| 3 |
That
you place us in funds sufficient to meet Counsel's fees.
| 4 |
That
you follow our advice in relation to the tactical approach to these proceedings,
retainer of Counsel and settlement. This is an area that you may wish to discuss
with me before we reach our agreement. As you know, in the past I have asked
you to give me an indication at what level you believe these proceedings ought
to be settled at. In the absence of such an indication my partners and I must
retain the ability to exercise our discretion in this matter.
| |
My
partners would also require personal guarantees from the Directors and Shareholders
of Floods of Queensferry Ltd in relation to this firm's fees.
| 6 |
Since
this firm would be required to "fund" an element of your company's costs we
would expect to agree terms whereby outstanding bills, any work in progress
that has yet to be billed, and disbursements carry interest charges at our
usual rates for outstanding bills.
| | |
I
look forward to hearing from you to fix a meeting to discuss these outline
proposals with you and with my Finance Partner. I am sure that you will appreciate
that these proposals are subject to entering into a formal agreement and to
its ratification by my Finance Partner."
| | | | | |
|
| 15. |
Mr Flood replied
on 30 December. Effectively he was happy to accept WF's offer to continue
but not on the terms proposed as FOQ had no money so that, for example, the
fees of counsel and experts would only be met if in some way Legal Aid continued
to be available. He raised the possibility of himself representing the company.
He also found paragraph 4 to be unacceptable, although it clearly followed
from the basic proposition that WF had put forward. However he said that he
and his brother, Mr Antony Flood would find £75,000 so that the stay could
be lifted. On 30 December a summons was issued to join Mr Flood as a party.
A meeting was arranged for 10 January 1997 with Mr Gwillim but it was inconclusive
as neither side moved. Mr Flood told Mr Gwillim that the experts (Mr Pennington
and Mr Jones) were expecting to be instructed (and paid) by WF. Mr Flood recorded
his position in a long letter of 13 January. It is a good instance of the
combination of Mr Flood's obsession with the case and his ability to deploy
the results of his researches (the accompanying five pages of extracts from
the Legal Aid Handbook have been omitted):
| | |
| |
"I
am extremely disappointed and concerned at the negative attitude Winward Fearon
have adopted to my case. As your client I am entitled to proper care, conduct
and advice, but your partners seem mainly interested in their fees. In this
regard, as an assisted person, I consider your attempts to extract guarantees
from me, that I am obviously not able to give, to be wholly improper. I should
also add that Richard Winward's refusal to see me on Friday, after I had come
to London for that purpose, was totally inexcusable.
| | |
As
you have become so focused on your firm's position, and before our relationship
deteriorates further, I want you to try to think constructively about a more
positive approach to the legal position of the case, both generally and specifically
with regard to the Legal Aid Board. I apologise if anything I advance is technically
or legally incorrect but at least it will balance the otherwise negative and
prejudiced views that you seem to have formed towards the future of the action.
You must understand that I am putting these views forward out of concern for
the case as a whole, in which both yourselves and the Legal Aid Board now
have a substantial cost interest along with myself.
| | |
| 1 |
My
original application was for Joinder, not Substitution. This was amended at
the hearing between Counsel and Judge Thornton. When giving judgment I believe
Judge Thornton, albeit briefly as a formality, joined me before making me
a substitute Plaintiff. If I was once joined as a Plaintiff, could it be possible
that the effect of the Appeal Decision was to revert me to being a joint Plaintiff,
i.e. that the recent decision does not, in fact, remove me from the action.
I mention this because you may not have considered it and there may be a point
on costs to be raised to the other side ahead of the proposed application
hearing on 24 January, in the event that I am applying for what I already
possess.
| | 2 |
Assuming
the Joinder application is required, I would ask you to remember that, based
on my assignment from Queensferry, I remain, regardless of the Appeal Decision
and the position under clause 2(3) of the Blue Form, the only interested person
in the outcome of this action, because all sums due are due to myself only.
Once a sum is judged to be due to the Plaintiff it will come to me directly
and not through the company. In these circumstances I cannot accept that I
am not legally entitled to be joined in the company's action, based on my
total and legitimate interest in its outcome. As there is a Section 51 application
against me then it is clear that the Defendants intend to proceed against
me personally for their costs. This fact further legitimatises my right to
be joined.
| | 3 |
As
regards the position of the Legal Aid Board I would urge you to read the relevant
notes for guidance in the handbook. If I am joined with Queensferry, the question
that arises under Regulation 32 of the Civil Legal Aid Regulations 1989 is
whether there are other persons (i.e. Queensferry) that have the same interest
as myself (the applicant) in the outcome of the action. As all sums due will
flow directly to me under the assignment then the answer must be that Queensferry
does not have the same interest as myself. The Appeal Court clearly did not
remove me from the action but found, wrongly in my view, that the assignment
was not valid in respect of sums not yet due pursuant to a judgment. Whilst
it sent the contractual claim back to the company it did not say that I have
no interest in the action or find that the assignment was invalid in respect
of sums due. In this connection I would remind you that there are sums due
but for the counterclaim. If you do not agree with my view on these points
I request that you explain the position as you see it.
| 4 |
While
Queensferry is a party to the action, it has no means to proceed with, and
no interest in the outcome of the action. In these circumstances I would be
totally prejudiced by not being joined as a party and by not having the continuing
support of the Legal Aid for which I qualify, in order to realise what I am
due. If Queensferry were means tested as to its ability to contribute to the
proceedings, or to go it alone, then it would be found to be incapable on
both counts.
| 5 |
Judge
Thornton said the clause 2(3) proviso gave rise to a crisp point of law. I
think it may be simply that and nothing more. In other words, provided I am
joint Plaintiff, the Court of Appeal ruling should not have any practical
impact on this action. If that is so then the only question that arises is
why the Appeal took place?
| 6 |
On
the point of contract/quantum meruit and the alternative claims against D2/D3.
Apart from the practical considerations we have raised in respect of the facts
of the case which have indicated that you will not even consider, it is particularly
necessary to protect the Legal Aid Board against fruitless litigation. As
D1 is insolvent, but for a parent guarantee that has not been produced in
evidence, there is clear reason to retain the claims against D3 as the only
solvent Defendant.
| | | |
| | |
I
request that you, and all of your partners, take careful note of my concerns
and consider the points I have raised before taking any decisions that we
may all regret. I would also appreciate it if you would apply yourselves to
supporting and not undermining my action. To help you consider the position
I am sending you extracts from the Legal Aid Handbook with relevant sections
highlighted with asterisks. Please look thoroughly and carefully at these
aspects and try to at least give me some faith that you are looking at the
position of the case with my interests in mind."
|
| | |
SCL relied
on parts of this letter, such as paragraph 2, as showing that Mr Flood realised
that the possibility of an order being made against him under section 51 was
real.
| | 16. |
In reply Mr Gwillim
sent two letters on 14 January. The first explained clearly what Mr Gwillim's
duties were to the Legal Aid Fund and to Mr Flood and dealt with Mr Floods's
numbered points and gave him a clear and correct warning that FOQ's claim
for a quantum meruit depended on establishing in fact and in law an entitlement
to be paid for what it had done. The second essentially reiterated the
terms of the letter of 23 December, including the requirement for a guarantee
from Mr Flood (no doubt since WF thought that Mr Flood would ultimately have
substantial assets). He attached a copy of the letter for Mr Flood and FOQ
to sign. Mr Flood and Mr Antony Flood wrote on behalf of FOQ on 20 January
1997 to decline the offer in WF's second letter as FOQ had no money to instruct
a solicitor and would not receive anything as it had assigned its rights so
Mr Flood would be paid. However in other letters of 20 and 27 January Mr Flood
asked WF to do eight things such as: to advise him; to apply to join him and
to represent him on that application; to defend him on SCL's application under
section 51; to instruct at least one other counsel on aspects of the case.
It seems that WF agreed to some of these requests since it did act on Mr Flood's
behalf in the application to join him. Following a hearing on 31 January that
application succeeded but I refused Mr Flood's own application to represent
FOQ (see 81 BLR 49).
| 17. |
Mr Flood's efforts
then concentrated on getting WF to persuade the Legal Aid Board to provide
Mr Flood with Legal Aid to prosecute the claims of FOQ as he was the beneficiary
of its rights against SCL. However on 24 February Mr Benjamin Levy advised
that whilst Mr Flood would have no prospect of success, the Legal Aid Board
might accept that he had a fiduciary capacity for the purposes of Regulation
33. FOQ was however able to meet the order for security by providing a bank
guarantee so on 24 February the stay was lifted. On 4 March 1997 Mr Andrew
Stafford gave qualified and basically negative advice to Mr Flood about his
prospects of success on the claim for a quantum meruit. In it he expressed
the view, based on material from Mr Jones, that FOQ should recover more than
the amount of the payment into court but only on the basis that it presumably
represented less than the defendants' estimate of their liability (see paragraph
14). He later informed WF that he would not alter his advice as he had lent
over backwards to give the most favourable advice for the purposes of Legal
Aid and that he did not wish his name to appear on the pleadings which were
to be amended to plead a restitutionary claim against the second and third
defendants.
| 18. |
In March 1997 Mr
Flood raised the possibility of obtaining legal costs insurance if it proved
impossible to get Legal Aid. The trial fixed for April was adjourned to October
1997 or January 1998, depending on readiness. On 26 March 1997 WF told Mr
Jones and Mr Pennington (in separate letters) that each would have to continue
relying on Mr Flood to pay his fees as WF had no funds and there was no Legal
Aid funding for his services. Mr Pennington accepted this. On 2 April 1997
Mr Flood had a meeting with Mr Winward who set out the terms upon which WF
would continue. It was made clear to Mr Flood that Legal Aid cover had effectively
ended, although the Chester Area Office said that cover would not be withdrawn
at that stage. WF had sent the Area Office a reassuring letter on 4 April
in which it was said "Estimated recovery is £1.2 million plus costs..". Mr
Rideout said that neither he nor Mr Jones produced that figure, but I doubt
it, as Mr Rideout was the author of other comparable figures, for which little
or no rational justification was provided, (and certainly none is apparent
from the documents and evidence that I have heard). A similarly optimistic
assessment was made in WF's letter of 23 April to the Area Office, and a file
note of 9 May 1997 (£750,000). Mr Winward followed the meeting up by his letter
of 15 April, and a chasing letter of 28 April. The letter of 15 April was
as follows:
| | |
| |
"Dear
David
| | |
Further
to our meeting on the 2 April I have now spoken to my Partners as to the basis
on which we might go forward to get this matter to trial in January next year
or October this year or indeed satisfactory settlement. As you know these
arrangements will only come into effect if and insofar as your Legal Aid Certificate
does not cover the requisite preparatory work. I also confirm that we will
continue our negotiations with the Legal Aid Board to secure the widest possible
cover from your Certificate. In this respect you will have received a copy
of the Legal Aid Board's letter dated 8th April which is encouraging.
| | |
As
you know we are not permitted by our professional rules of conduct to conduct
contingency fee litigation save in a limited respect not relevant to this
case. I consider that such a situation will not arise provided you give me
your personal guarantee to pay the costs and disbursements incurred on behalf
of Floods of Queensferry. You stated that you understood this point and were
agreeable in principle to a guarantee. Accordingly I now set out below the
terms upon which Winward Fearon will continue to represent Floods of Queensferry
namely:-
| | |
| 1 |
You
will execute the personal guarantee in the form attached and will procure
that Floods of Queensferry Ltd also executes the guarantee.
| 2 |
You
and Floods of Queensferry will give a written undertaking to pay all or any
proceeds of settlement with the Defendants or judgment of the court into his
firm's client account without deduction and you and Floods of Queensferry
agree to permit us to deduct our costs from client account money whether or
not those costs are outstanding now or relate to work between now and the
date of any settlement or judgment.
| 3 |
You
will be responsible for direct payment of all experts' fees and costs of photocopying.
| 4 |
Our
charges will be calculated on a time basis at an hourly rate of £275 per hour.
The work will be mainly undertaken by Barry Rideout and David Gwillim. Insofar
as we use junior solicitors or trainees the hourly rate will be £150 per hour
and £90 per hour respectively.
In
addition we shall charge VAT and the costs of disbursements.
| | 5 |
We
shall have the right to choose the Counsel to represent you at the Hearing
and/or whether or not David Gwillim represents you at that Hearing with or
without Counsel.
| | 6 |
A finance charge of 3% per annum above the prevailing base rate shall be charged
in respect of the outstanding invoices identified in the schedule attached
to this letter to be calculated from the respective dates of the said invoices
until date of payment.
| 7 |
We
agree not to issue any further bills until the end of the trial in this matter
or settlement or compromise of the action whichever is the earlier.
| | | | |
| | |
I
enclose a copy of this letter which I should be obliged if you could please
sign to signify your agreement to its terms and return to me. This letter
is a contentious business fee agreement and by signifying your approval to
the rates set out above you agree that our costs shall not be subject to Taxation
and you waive the Company's statutory rights in that regard.
| | |
Nothing
in this letter is to be taken as affecting the personal position of D C Flood
vis a vis the Legal Aid Fund."
|
| | 19. |
No reply was sent
by Mr Flood until a brief acknowledgement on 31 May 1997. By that time a proposal
for Legal Cost Insurance had been submitted. The intention was to replace
WF's requirement for a personal guarantee from Mr Flood. The proposal form
was signed by both Mr Flood on behalf of FOQ and by Mr Gwillim. It estimated
the claim to be worth "£900,000 to £1,500,000", and the prospects of success
to be "very good". These entries came from Mr Rideout, who admitted that he
had not done any exercise to arrive at the figures. On 23 May Mr Rideout had
sent a candid fax to Greystoke in which he had said:
| | |
| |
"We
are posting to you without a covering letter the Report of Mr Richard Jones,
the expert Quantity Surveyor dated 10 June 1996 which was provided on an interim
basis. The report identifies claims amounting in all to £1,240.000.00. I have
this morning spoken to Mr Jones regarding the figures contained in his Report.
| | |
The
practice of inflating a legitimate claim is so endemic in the construction
industry, that it is not possible to mount a genuine claim and conduct it
to a conclusion without such inflation. Mr Jones' original claim and the figure
of £1,245,000 contains an element of excess which neither Mr Jones nor Mr
Flood would expect to recover at a trial of the issues. However, there are
indications that some of the figures and claims made by Mr Jones are less
than they might have been, had he been aware of the full situation at the
date of the interim report. Mr Flood having reviewed the figures, places a
value upon the claim of £600,000 plus interest. Mr Jones asked to give a conservative
recovery figure suggests £500,000. Mr Flood in arriving at his figure of £600,000
has made an allowance of £22,500 towards the counterclaim made by the Defendants.
Mr Jones makes no allowance for the counterclaim on the grounds that it is
wholly unsustainable without a fully pleaded causation and in respect of which
there has been no discovery.
| | |
A
rough calculation of interest would give a figure of approximately one third
additional to the recovered sum. That would give an anticipated recovery of
between £800,000 and £650,000.
| | |
In
addition, under the terms of the main Contract, the main contractor has a
duty to seek to recover monies due to the sub-Contractor and on payment of
monies from the client to the main contractor in respect of works conducted
by the sub-Contractor to pay over such sums.
| | |
The
main contract the contractor has recovered a sum of £185,000 in respect of
works solely undertaken by the sub-Contractor. Those figures however have
not appeared in any of the allowances, calculations or considerations of the
sub-Contractor's account. Knowledge of the payment only came to light as a
consequence of discovery of documents and was not admitted by the Defendants
at the time of their Affidavit evidence before the court on summary judgement.
The Official Referees courts have, in the past, taken a dim view of main Contractors
failing to meet their obligation to pass over monies to the sub-contractors
where they themselves have received payment. In the present instance, the
Court could as a matter of discretion award either on that sum or the whole
damages a superior rate of interest or permit interest to be compounded. Also
in such circumstances, it is not unknown for a Court on accepting that such
conduct has taken place, to be more inclined to lean towards the claimant
and give the benefit of the doubt to the claimant rather than the Defendant.
Because of these factors, we do think that the figure put forward by Mr Flood
and Mr Jones can genuinely be accepted as a conservative recovery.
| | |
The
quantity surveyors for the parties have been engaged in 'without prejudice'
discussions to agree facts and identify issues, pursuant to the Courts directions.
The extent of agreement between them is extremely limited and comprises primarily
quantities and calculations. The Defendants QS has refused to agree even matters
upon which there is overwhelming evidence.
| | |
This,
therefore cannot be regarded as a case where the parties are likely to come
together in their thinking upon quantum.
| | |
The
Defendants' tactics both prior to the institution of proceedings and subsequently
have been of attrition to exhaust the Plaintiffs financially. The Defendants'
primary tactic and expectation has been that the Plaintiffs would run out
of funding. The certainty that this action is financed sufficiently to go
to trial is as likely to provoke settlement as anything."
|
| 20. |
Mr Flood said that
he received a copy of the fax at the time. I am sure that it reflects his
views, including the last paragraph. Mr Flood agreed that the figure for "anticipated
recovery of between £800,000 and £650,000", including an additional one third
for interest represented the amounts then contemplated. However a few days
after signing the proposal form Mr Flood complained to Mr Gwillim about Mr
Rideout's "lack of competence" and being a loose cannon capable of doing untold
harm to the strength of my case". Mr Rideout said that he completed the form
for Mr Flood to sign so I do not suppose Mr Flood's complaints were about
the optimistic statements made in it. Mr Winward required the insurance to
be completed but Mr Flood was reluctant to do so. By 6 June WF was owed nearly
£90,000 (inc VAT) for its non-aided work and had only received two payments
totalling £3,000. Mr Flood's application for Legal Aid in his "fiduciary"
role was refused but there was an appeal. On 23 June Mr Winward wrote to Mr
Flood to tell him that if the appeal were unsuccessful then Winward Fearon
would cease to act unless it had an executed fee agreement by 27 June and
he enclosed again a letter agreement for Mr Flood to sign. On 24 June the
appeal was dismissed. Mr Winward wrote again on 1 July 1997 in the much the
same terms as his previous letter of April, although there were certain modifications,
e.g. to deal with the fact that legal costs insurance had now been obtained.
| | |
| |
"Dear
David
| | |
Further
to our meeting on the 2 April I have now spoken to my partners as to the basis
on which we might go forward to get this matter to trial in January next year
or October this year or indeed satisfactory settlement. As you know these
arrangements will only come into effect if and insofar as your Legal Aid Certificate
does not cover the requisite preparatory work. I also confirm that we will
continue our negotiations with the Legal Aid Board to secure the widest possible
cover from your Certificate. In this respect you will have received a copy
of the Legal Aid Board's letter dated 8 April which is encouraging.
| | |
As
you know we are not permitted by our professional rules of conduct to conduct
contingency fee litigation save in a limited respect not relevant to this
case. I consider that such a situation will not arise provided you give me
your personal guarantee to pay the costs and disbursements incurred on behalf
of Floods of Queensferry. You stated that you understood this point and were
agreeable in principle to a guarantee. Accordingly I now set out below the
terms upon which Winward Fearon will continue to represent Floods of Queensferry,
namely:-
| | |
| 1 |
There
is in place legal costs indemnity in sums agreed between us which may be subject
to enlargement if required. Accordingly the personal guarantee in the form
attached is not required until such time as the legal costs indemnity is exhausted.
| 2 |
You
and Floods of Queensferry will give a written undertaking to pay all or any
proceeds of settlement with the Defendants or judgment of the court into this
firm's client account without deduction and you and Floods of Queensferry
agree to permit us to deduct our costs from client account money whether or
not those costs are outstanding now or relate to work between now and the
date of any settlement or judgment.
| 3 |
You
will be responsible for direct payment of all experts' fees and costs of photocopying.
| 4 |
Our
charges will be calculated on a time basis at the following hourly rates,
namely:-
David
Gwillim £275 per hour
Barry
Rideout £240 per hour
Junior
Solicitors £150 per hour
In
addition we shall charge VAT and the costs of disbursements.
| 5 |
We
shall have the right to choose the Counsel to represent you at the Hearing
and/or whether or not David Gwillim represents you at that Hearing with or
without Counsel.
| 6 |
A
finance charge of 3% per annum above the prevailing base rate shall be charged
in respect of the outstanding invoices identified in the schedule attached
to this letter to be calculated from the respective dates of the said invoices
until date of payment.
| 7 |
We
agree not to issue any further bills until the end of the trial in this matter
or settlement or compromise of the action whichever is the earlier.
| | | | | | |
| | |
I
enclose a copy of this letter which I should be obliged if you could please
sign to signify your agreement to its terms and return to me. This letter
is a contentious business fee agreement and by signifying your approval to
the rates set out above you agree that our costs set out in the Schedule attached
hereto but not further or otherwise shall not be subject to Taxation and you
waive the Company's statutory rights in that regard.
| | |
Nothing
in this letter is to be taken as affecting the personal position of D C Flood
vis a vis the Legal Aid Fund."
|
| | |
Although
the letter did not specifically repeat what had been said in June, namely
that without an agreement WF would cease to act, there is nothing in the letter
which is inconsistent with that intention and its form and content are consistent
with that intention.
| | 21. |
Mr Flood replied
at length on the same day. He said that he intended to appeal against the
appeal decision, that he had paid for legal costs insurance cover of £50,000
to deal with costs incurred by FOQ which fall to the company outside the scope
of any Legal Aid coverage, and that he could not "give proper consideration
to the terms of your firm's offer" without further details which he said that
he had not received. Most of Mr Flood's requests were designed to embarrass
but they were essentially irrelevant and, as usual, his letter was calculated
to divert attention from what had to be done by him. Not surprisingly Mr Winward's
answer on 4 July was relatively short, and having reminded Mr Flood that he
had been given the information that he had asked for, rightly described the
remainder of Mr Flood's letter as "unhelpful". "However I propose to make
an allowance for the stress that you have been under recently. May I suggest
that our joint energies be directed towards winning your case rather than
engaging in hostile and negative correspondence". WF continued to act for
FOQ since Mr Winward thought that WF's costs would be covered by the insurance
and it had made it clear that it was not liable for experts' fees. Mr Rideout
submitted a very bullish note to the Legal Aid Board in August 1997, which
Mr Flood saw later. I do not consider that he disagreed with it. It set out
factors which had apparently been taken into account in considering the possibilities
of settlement. They included the view of WF that "the only reason this action
has proceeded this far is that the defendant's solicitors and their client
believe that they can defeat the plaintiffs financially. .... Following the
hearing of 10 October next that delusion can no longer be maintained."
| 22. |
The insurance policy
was effected by early July. I shall call it the Greystoke insurance policy
after the brokers or agents. I shall set out its terms when I deal with Issue
5. According to an affidavit by the directors of FOQ sworn on 5 May 2000 the
premium of £2,740 for the insurance cover was lent by Mr Flood's mother to
Mr Flood who in turn lent it to the company. The cover was subsequently increased
to £100,000 in early January and then to £200,000 in December 1997 (effective
from 22 January 1998) with the additional premiums being financed in the same
way. The total amounts lent to FOQ by Mr Flood between 30 January 1997 and
13 December 1999 came to about £66,000, some of which came from other sources.
| 23. |
Legal Aid was obtained
on appeal for FOQ on the grounds that it was acting in a fiduciary or representative
capacity. The Legal Aid Board declined to issue the certificate but in October
1997 an order was obtained for its issue. However the Board was successful
in persuading Popplewell J to quash the decision in an application for judicial
review. An appeal against that judgment was dismissed by the Court of Appeal
on 18 December 1997. Its effect was that Legal Aid was no longer available
to prosecute the claims of FOQ (see for example the judgment of Millett LJ
at pages 12-14 of the transcript).
| 24. |
A PTR was held on
28 November when directions were given for the trial to start on 12 January.
I had previously directed that the trial should deal with FOQ's claim under
and for breach of the contract with SCL (and SCL's counterclaim) and would
not deal with other issues such as the claims made by Mr Flood personally.
About a month earlier the defendants offered the claimants £500,000 inclusive
of costs as an overall settlement. Mr Flood however wanted to know how the
costs would be dealt with as he thought "it would make settlement easier to
achieve and give us a negotiating advantage". I am sure that WF did not withhold
any such information about costs from Mr Flood, contrary to the impression
conveyed by Mr Flood. A letter was sent on 17 November to record and to repeat
the offer. It was rejected on 21 November. WF said that it "would advise our
clients to accept £2.5m now, inclusive of interest and costs". It is very
difficult to see how this figure could have been arrived at, unless it was
intended to ensure that WF, counsel and experts were fully paid at their billed
fees and on an indemnity basis, without taxation. The estimate used in the
summer was £600,000 to £850,000 inclusive of interest. Mr Rideout's note of
November said that "Flood will take £700K clear." Mr Flood would have been
very happy with that. I accept the submission made by Mr Reese that one can
reasonably infer that of the £2.5 million probably about £700,000 has been
included for the claim (and may thus be compared with the £350,000 paid into
court). Mr Flood also said that as the trial approached he became less confident,
although one would not have known it from his manner. (It appears that after
the decision of the Court of Appeal in December 1996 leading counsel for SCL
was instructed to tell junior counsel for FOQ that the offer might be increased
to £600,000 all in but I do not consider that such an intimation reached Mr
Flood.)
| 25. |
In my view the real
reasons for any lack of confidence (if true, which I doubt) could only have
been as follows. First, he knew of FOQ's finances during the contract and
that (as I recorded earlier) FOQ's site costs were about £1,115,000. Allowing
10% (as I did) for overheads and profit, FOQ would have been fully compensated
if it had received £1,223,000. It had already been paid £831,000, i.e. some
£392,000 short of that ideal target. However if the effect of the credit notes
were taken account the figure for site costs reduces by some £200,000. Even
if the position were considered from the point of view of the Flood family
interests FOQ had through the use of credit notes avoided a significant amount
of VAT. So it is remarkable both that SCL's payment into court was not treated
as a sensible offer and that in November 1997 no sensible counter offer was
made to SCL's offer. The amount of interest would or should have been not
material, given FOQ had ceased to trade and given that the amount in court
was earning interest. Secondly, the plan to keep the action going in the hope
that the defendants' offer would be increased had not worked. Each side had
determined on a war of attrition; each must have been concerned not just that
seemingly unlimited resources were being found but that there were no signs
of any retreat, still less capitulation. The amounts at stake did not justify
a trial of a classic construction dispute, much of the costs of which would
spent on investigating issues out of all proportion to the sums recoverable.
I am sure that neither side wished the trial to take place. So it would only
be natural if Mr Flood's was getting cold feet, especially since WF would
return again to require an agreement whereby the trial could be financed.
| 26. |
However, on the
basis of information provided by Mr Gwillim and Mr Rideout, Mr Winward continued
to believe that, taking account the amounts that might be recovered from Legal
Aid, the amount insured would be enough to cover WF's base costs. In his second
witness statement he said:
| | |
| "46. |
By early January 1998, I was satisfied that there was sufficient funding in
place to cover Winward Fearon's costs of the trial. This was on the basis
of the insurance cover of £200,000 (which I understood would be available
to meet Winward Fearon's costs), the payment on account received by the Legal
Aid Board (approximately £200,000 exclusive of VAT) and the further sums due
from the Legal Aid Board (anticipated to be in the region of £100,000). On
the basis of the 28 day time estimate, I calculated that counsel's fees would
amount to approximately £180,000 (on the assumption that Simon Hughes fees
would amount to roughly half of those of Tim Elliot [£65,000, plus a refresher
of £2,000]). Taking into account Barry Rideout's base cost for attending the
trial (approximately £20,000), this left approximately £300,000, which I considered
would be sufficient to cover Winward Fearon's base costs and disbursements
to date, and provide a profit (albeit modest in comparison with the profit
margins on Winward Fearon's mainstream business). I did not include experts
fees in the calculation, since I had insisted, and been assured, that Winward
Fearon was not to be responsible for these.
| 47. |
On the basis of my calculation, I was prepared to permit Winward Fearon to
continue to act for FOQ and to represent it at trial. Of course, I also had
in mind that, were FOQ to succeed on liability and beat the payment into court,
FOQ's costs would be recoverable from the Defendants. As I have indicated
previously, I had been told that FOQ was almost certain to be successful at
trial and beat the payment in. Nevertheless, I would not have been prepared
for Winward Fearon to continue acting had I not been satisfied that it was
covered for its base costs, disbursements and counsel' s fees.
| |
| | |
It is
not easy to see how Mr Winward could arrive at these views. He had not tested
the advice given and he must have relied on Mr Gwillim and Mr Rideout to assess
the probability of beating the payment into court. In November 1997 he had
been presented with a cost estimate from Mr Rideout which listed time recorded
as £860,000. Counsel's fees then amounted to £116,753 and disbursements came
to £66,167. Mr Winward struck out experts' fees of £333,089 but with some
other costs the total was still above £1 million, with the costs of the trial
still to come. A further estimate of 21 November for the trial put WF's costs
at about £180,000, the experts at about £85,000, counsel at about £145,000
with copying and disbursements at £20,000, or some £430,000. Nevertheless
since Mr Winward said that he discussed the position with Mr Gwillim, that
his concern was for his firm's base costs and since, when giving evidence,
he effectively answered the criticisms put to him, I conclude with some reservations
that, on the assumptions made by Mr Winward, e.g. that WF would not be liable
for experts (and presumably copying and disbursements would be funded) the
amount of insurance cover would have met his firm's base costs, but the amount
of profit on the work would have been not just modest but probably negligible.
WF's decision could only have been justified commercially by what it expected
to get for the work done when Legal Aid was available (the estimates for which
varied but was likely to be about £250,000). It averted the crisis facing
Mr Flood and FOQ and enabled the trial to start.
| 27. |
The trial lasted
longer than expected. Mr Winward maintained that its effect was no more than
an "erosion of the profit return". I suspect that this is a tactful under-statement,
and likely to be unrealistic and improbable, but I cannot find that it was
wrong, as I do not have material to decide the effect of the assumptions made
by Mr Winward. However Mr Winward rightly said that there was then no question
of WF coming off the record as that would be contrary to its professional
duties. In my view the true position may be seen by Mr Winward's letter to
Mr Flood of 15 May 1998. The letter was prompted by the parlous position of
Mr Jones, upon whose evidence on quantum FOQ's case had largely depended.
WF had made it clear throughout that it was not liable for the fees of experts
such as Mr Jones and Mr Pennington (who by then was also seriously concerned
about the balance of his fees amounting to £173,700). At a meeting on 12 May
Mr Flood maintained that "FOQ had no formal agreement with RJ about his fees"
and was not even prepared to meet WF's offer to advance Richard Jones £5,000
if it was matched by FOQ, although Mr Jones' evidence was crucial. (Mr Flood
met other expenses during the trial of about £27,000.) Mr Flood was also told
about counsel's fees which were then said to come to £400,000. Mr Winward's
letter confirmed what Mr Flood had been told:
| | |
| |
"I
refer to our discussion earlier this week. I have today spoken with Richard
Jones. I fully understand that having received no monies on account of his
professional fees since the end of 1996, his position is a most difficult
one. As I have advised you and as I reminded him this office has no legal
obligation for his fees (beyond accounting for the Legal Aid period costs)
however his whole hearted commitment is still required through to the conclusion
of the trial at the end of June.
| | |
As
a result of my discussion with Richard it is proposed that Richard will provide
an invoice for a notional sum generally on account of professional fees since
the 1st April 1998 for which this office would be responsible for half upon
an ex gratia basis and you would seek family support for the same proportion.
| | |
As
a condition of our accepting this additional burden I must resolve the hourly
rates for the non-Legal Aid work. I propose the following:-
| | |
| |
From
the initial instruction of this practice in January 1995 the rate previously
agreed with Tim Reynolds of £175 per hour would remain applicable until the
31st December 1995. From the 31st December 1995 to the 31st December 1996
the non-Legal Aid rate be £220 per hour for Tim Reynolds, David Gwillim, Peter
Smith and Barry Rideout and £70 per hour for trainees and £25 for para-legals.
| | |
For
the period 1 January 1997 to 1 January 1998 the rates will be £240, £80 and
£25 respectively.
| | |
For
the period from the 1 January 1998 and continuing the rates will be £250,
£75 and £30.
| | |
These
rates will only apply to non-Legal Aid work. Legal Aid costs are a matter
for taxation in any event.
|
| | |
I
reaffirm my comments made to you that I wish to view the final cost position,
if at all possible, on the basis that damages recovered are not depleted by
a liability for this offices costs. By this I intend that this office should
be content with the costs which are recovered under the Legal Aid Certificates
and against the Defendants. Because of the complexity of the costs situation
I cannot at this point in time formally confirm that we would not seek payment
of solicitor and client costs as we cannot know before taxation what proportion
of the costs incurred will in the view of the Taxing Master be solicitor and
own client costs. Where we have undertaken work in making applications for
Legal Aid and dealing with Appeals and other steps in respect of Legal Aid
for the limited company we will not look to recover those costs.
| | |
There
will be a liability for costs awarded to the Defendants which Barry informs
me includes
| | |
| (a) |
The
amendment of Pleadings.
| (b) |
Security
for costs application.
| (c) |
Substitution
and joinder to the proceedings and appeals to the Court of Appeal.
| (d)
|
6th
August 1997 Hearing.
| (e) |
The
application to personally represent the limited company.
| | | | |
| | |
(This
list is not conclusive). Such costs will have to come out of any judgment
sums.
| | |
It
will be necessary for any monies paid by the Defendants to be paid to this
office and to be held by this office under the terms of the Legal Aid Board's
Statutory Charge.
| | |
Whilst
writing I would confirm that we have discussed the practice involved in taxation
of costs and I have outlined to you alternative ways of dealing with the non-Legal
Aid costs that may be recovered from the Defendants which would allow for
their resolution without formal taxation."
|
| | |
Mr Winward
therefore made it clear, quite understandably, that WF would have to be content
with what it could get from the Legal Aid and from the defendants or the insurance.
At that stage there was still optimism that the payment in would be beaten.
Mr Flood did not reply to this letter and in evidence could not say clearly
how he dealt with this request, which was noteworthy. (Mr Flood has always
been positive when he was sure that the answer suited his case but not otherwise.)
WF itself generously made an ex gratia payment of £10,000 to Mr Jones to help
him. Mr Pennington's fees however remained unpaid.
| 28. |
After the conclusion
of the trial of the issues the amounts owing by FOQ was recorded in April
2000 by its accountants in a letter to Mr Flood as follows:
| | |
"Floods
of Queensferry Limited
| | |
Further
to your recent request we set out below a breakdown of Creditors as disclosed
within the Company's accounts for the year ended 31 March 1999:
| | |
| (a) |
Accrued
Expenses
| | |
Winward
Fearon outstanding fees, disbursements, counsel's fees and work in progress.
|
|
£
|
|
| | |
Period
to 12 January 1999
|
1,381,235
|
|
| | |
Estimate
for expert witness fees outstanding
|
119,315
|
|
| | |
Period
1 April 1999 to 30 April 1999 (Counsel's Fees)
|
5,749
|
| |
£1,506,299
|
| (b) |
Other
Creditors
| | |
Balance
due to Floods Properties and Development Co Limited £8,350
| (c) |
Director's
Current Account
| | |
Floods of
Queensferry Limited
| | |
Director's
Current Account
| | |
As at 31
March 1999
DR CR
| | |
Balance
brought forward 0 0
| | |
Year ended
31 March 1997
| | |
Liabilities
taken over by DC Flood – Church & Church, Richard Jones 57977.27
| | |
Year ended
31 March 1998
| | |
Monies introduced
02/08/97
1500.00
08/07/97
300.00
14/08/97
500.00
06/01/98
4110.00
18/01/98 10960.00
17370.00
| | |
Year ended
31 March 1999
| | |
Expenses
paid privately
| | |
Hotels,
general, trains, subsistence etc 27387.00
| | |
Legal costs
insurance – Greystoke 2740.00
| | |
Expert witness
fees – Mr Ian Pennington 11000.00
| | |
Security
charges – HSBC 3875.00 45002.00
120349.27
Rounding
1.73
| | |
Balance
carried forward as at 31 March 1999 152551.00
120351.00 120351.00
(By this
time counsel had agreed to forego the balance of their fees which had not been
paid by WF which in each case was a very substantial sum.) Mr Flood agreed that
FOQ was liable for Mr Pennington's fees. It is clear that WF did not agree to
pay Mr Pennington's fees on behalf of FOQ, still less itself, and was indeed
at pains to make it clear that it would not accept liability for the fees of
experts.
| | |
| | |
Issue 1: Did
the second claimant, Mr David Flood, fund and/or maintain and/or finance the
proceedings, or any part thereof, brought by the first claimant against the
defendants?
| 29. |
SCL voluntarily
amplified its claim against Mr Flood on 13 June 2000. It submitted that it
did not need to do so as an application under section 51 was a summary procedure.
A summary procedure is the normal one where the application depends on what
took place in the course of the proceedings and the trial. However, as I said
when declining to allow SCL to advance a case against WF under section 51(6)
and (7) as part of these present proceedings, an application under section
51 can be made and decided by a non-summary procedure where it is just to
do so, such as where, as here, the facts relied on came to light after the
trial and were not and could not reasonably have been known to the applicant.
The overriding objective set out in part 1 of the CPR would not be met if
such material was not available or could not be tested because a summary procedure
was adopted. The case against Mr Flood was that he was a director of FOQ but
that he did not act "in the proper and objective way that a company director
should act"; that he had a direct financial interest in the outcome; that
he knew that FOQ could not pay the costs if unsuccessful; that in 1996 he
was the substituted plaintiff; that he directly funded the proceedings; that
he persuaded WF to fund the proceedings and arranged for the insurance cover;
and that he arranged the credit notes.
| 30. |
Mr Flood denied
that he effectively controlled the proceedings. It was said that his attempts
to do so by following through the assignment and becoming the substituted
plaintiff were, paradoxically, thwarted by the defendants but for which the
order for costs made against FOQ would or might have been made against Mr
Flood, i.e. that now sought by SCL. Mr Flood did no more than a company director
of a family company. The loans made or procured by him (which came to £101,110)
were proper.
| 31. |
First, I do not
consider that Mr Flood funded or financed the proceedings. Obviously the proceedings
have been brought and continued primarily for his benefit, both as controlling
shareholder and as the company's principal creditor (leaving aside SCL's claims
and the claims of WF and others generated by the proceedings). That is frequently
so with a family company but it does not follow that the shareholders lose
the benefit of limited liability by supporting the company to protect their
interests. I have set out the main occasions upon which Mr Flood either directly
or indirectly assisted FOQ to continue the litigation, e.g. as set out in
the statements sworn by all three directors about the source of the funds,
and by providing security for the £75,000 by way of a charge on his house.
Leaving aside the latter, Mr Flood appears to me to have been able to find
or to have contributed from his own assets about £60,000, itself a significant
figure for someone who qualified for Legal Aid. It was suggested that the
amount was a very small part of the costs, but I do not think it is right
to use WF's assessments of about £2 million. That figure assumes recovery
on a ordinary basis from a solvent and well-disposed client at the rates put
forward by WF; it includes amounts recoverable from Legal Aid; it includes
fees of counsel and experts. Nevertheless it would not be a material contribution,
especially since it includes Mr Flood's own expenses. I do not consider that
providing a charge on the house and paying the bank's arrangement fee amount
to funding the action. Those behind any small company are liable to support
it if its assets cannot otherwise support the obligations inherent in litigation.
This is not funding in the sense of intervening. So too is the provision of
the Greystoke insurance: that is the same as the directors of a small company
providing the company's solicitors with security for fees.
| 32. |
The proceedings
have otherwise been funded on credit, itself provided by a mixture of circumstances.
First, there was the belief that the action would be successful and that there
would be judgment for more than the amount paid into court. I am satisfied
that that belief was sincerely held by those in WF responsible for the conduct
of the action. I am not satisfied that it was reasonably held by Mr Gwillim
(or Mr Rideout), but it may have been since privilege has not been completely
waived. Secondly, misfortune bred of misplaced trust and inexperience played
its part, certainly as regards the experts who provided their services apparently
without securing worthwhile agreements. Thirdly, WF appear to have found itself
trapped. It allowed the proceedings to continue without an adequate arrangement
for the payment of their fees. Having decided that the case of FOQ was worth
supporting or having allowed Mr Flood to think that it was sound it could
not bring itself to withdraw support and had therefore to hope that its fall
back arrangements would contain the position to acceptable limits.
| 33. |
Nor do I consider
that Mr Flood has acted improperly as a director. FOQ was a family company.
In paragraph 2 of my principal judgment I set out the relationship of some
of the Flood family companies. He was one of three directors of FOQ. Important
decisions were taken by all three. Mr Antony Flood's independent views can
be seen from paragraph 4 of the minutes of the FOQ Board dated 31 March 1992
(quoted in paragraph 277 of my principal judgment). However Mr David Flood
held 51% of the shares, and after the assignment of December 1995, had an
overwhelming financial interest in the outcome. As Mr Reese said, "the assignment
merely formalised the commercial reality". Even in January 1997 Mr Flood treated
FOQ's claim as his own - see paragraphs 2 onwards of his letter of 13 January
1997. Thus Mr Antony Flood's co-director's signature to the Greystoke proposal
form must be treated as a mere formality. Prior to the assignment I do not
consider that Mr Flood's endorsement of the prosecution of the case after
the payment into court was improper. He was duty bound to get the best settlement
for the company. I cannot conclude that a rational and competent company director
would then have seen the offer as providing more than its costs plus profit
(as well as its costs of the action). The claim was then seen as a contractual
claim. Few directors of companies operating in the construction industry,
especially directors of small private companies, test contractual entitlement
against actual cost plus profit. In addition FOQ had to consider its position
after the defence and counterclaim. The payment in followed an earlier offer.
Whatever the underlying weaknesses in FOQ's case (which I accept either Mr
Flood knew about or should have known about) it was not unreasonable to press
on in the hope of a better offer. After the assignment Mr Flood could not
divorce his personal interests from those of the company. They were now inseparable,
and to say that he acted improperly as a director from 1997 is to say that
he acted unreasonably and improperly when he was a substituted plaintiff in
receipt of Legal Aid. But many proceedings are brought and persisted in unreasonably
in the sense that they seek amounts to which the claimant is not in fact and
in law entitled, but the claimant holds a genuine belief that the claim is
good. Millett LJ started his judgment in Metalloy Supplies v M.A. (UK) Ltd[
[1997] 1 WLR 1613 at page 1619H]:
| | |
| |
"It
is not an abuse of the process of the court or in any way improper or unreasonable
for an impecunious [plaintiff] to bring proceedings which are otherwise proper
and bona fide while lacking the means to pay the defendant's costs if they
should fail. Litigants do it every day, with or without Legal Aid."
|
| | |
Lord Hoffmann
in Norglen[ [1999] 2 AC 1 at 19] said:
| | |
| |
"Having
to litigate against an impecunious plaintiff is a risk of litigation which
has to be accepted".
|
| | |
A defendant
has a number of remedies; it can ask the court to exercise powers which might
have the effect of confronting the claimant with the problems that it has
to face or which might lead to the case being struck out or otherwise curtailed;
it can make an offer or payment into court; it can apply for security for
costs where the claimant is impecunious. However an unreasonable litigant
whether claimant or defendant whose case has some merit and cannot therefore
be described as improper or lacking bona fides cannot otherwise be silenced
if the threat of an adverse costs order proves to be an ineffective sanction.
To this extent the defendants' quandary really stems from the order of Mr
Recorder Blunt QC for security of only £75,000 until the end of the trial
(i.e. without the usual provision for an amount up to a specific stage with
the opportunity of review). The amount ordered is explicable only as calculated
not to be oppressive to FOQ, even taking account the payment into court. However
the defendants had their opportunity to appeal. Quite apart from the judge's
view that the action was not being maintained it is therefore difficult to
conclude that its further prosecution of the case by FOQ was improper, as
opposed to being imprudent.
| 34. |
Clearly once Mr
Flood decided to harry the defendants and once the defendants had made it
clear that they were going to fight FOQ and Mr Flood every inch of the way
then in an ideal world a rational director would have taken stock. However
I doubt if he would then have been dissuaded from continuing. First, the defendants'
opposition did not necessarily mean that a better offer might not be forthcoming
eventually. Secondly, I do not consider that he would have been advised to
negotiate. Mr Flood was critical of his legal advisers and the lack of legal
advice. Since he refused to agree WF's terms he has only himself to blame.
In addition he knew the strength and weaknesses of FOQ's case at least as
well as any of his advisers so I see his criticisms as a typical manoeuvre
to deflect attention from his own decisions. Assuming that Mr Flood had been
really determined to be properly advised (and in my judgment, I have seen
no evidence of that intention - but of course it may lie behind the arras
of privilege) and that any of his advisers (counsel excepted) at any stage
understood how important it was to verify the basis of the claims, whether
contractual, for new rates, for day works, for remeasurement, for delay or
disruption or for breach of contract or misrepresentation. It does not appear
that Mr Flood was aware of the potential weakness of the claims for damages
that had been created by the credit notes until the eve of trial, at the earliest.
As frequently happens efforts were concentrated on establishing liability
at the expense of attending to quantum, despite the clear recognition in the
fax of 23 May 1997 that the claim was inflated. The payment into court should
have made it plain to FOQ's advisers that the vital question was whether causation
and quantum could be established. The quality of the first claimant's witness
statements and the statements and reports of Mr Jones indicated to me that
these areas had not been given sufficient attention. I doubt therefore if
Mr Flood would have received the advice that he now suggests that he should
have been given. The claim for misrepresentation could only have been advanced
on the basis of legal advice. It must for the purposes of the present issues
be treated as a claim that was made by FOQ bona fide although it ought not
in my view to have been brought to trial.
| 35. |
In Giles v Thompson[
[1994] AC 142] the House of Lords adopted and applied the description of the
policy of the tort of maintenance which had been expressed by Fletcher Moulton
LJ in British Cash & Parcel Conveyors Ltd v Lamson Store Service Co Ltd[
[1908] 1 KB 1006 at 1014]:
| | |
| |
"It
is directed against wanton and officious intermeddling with the disputes of
others in which the [maintainer] has no interest whatever, and where the assistance
he renders to one or the other party is without justification or excuse."
|
| | |
In the
Court of Appeal Sir Thomas Bingham MR had described it as an excellent working
description and emphasised that justification could usually be found in a
legitimate business interest. In my judgment although the motives for the
assignment of December 1995 were questionable it remained a legitimate manoeuvre
to get Legal Aid and when it proved unsuccessful it provided Mr Flood with
a good business reason to pursue the action towards a settlement, quite apart
from his other interest such as his position as a director of a family company
and the assignment of the claims of Church & Church and Mr Jones. Since
someone has to manage and control litigation on behalf of a company I do not
consider that Mr Flood should be regarded as having maintained the proceedings
for the purposes of issue 1. There was no one else who could have done so.
The issue will therefore be answered: No.
| | |
Issue 2: Is it just in all the circumstances to make Mr David Flood pay the unrecovered
costs (or a proportion thereof or a fixed lump sum representing a part of
the unrecovered costs) of the proceedings?
| 36. |
The answer to issue 1 (whichever it is) does not necessarily lead to the answer to Issue 2. There
must be some good reason why a person who is not a party to an action should
be liable to an order under section 51. The starting point for a consideration
of the factors that might be taken into account may begin with the judgment
of Balcombe LJ in Symphony Group Ltd v Hodgson[ [1994] QB 179 at pages 192-3]:
| | |
| |
"I accept
that these categories are neither rigid nor closed. They indicate the sorts
of connection which have so far led the courts to entertain a claim for costs
against a non-party. However, it seems to me that the particular circumstances
of this case require this court to accept the invitation of Lord Goff in the
Aiden Shipping case and to lay down some principles for the guidance of judges
of first instance when they are asked to make an order for costs against a
non-party and in doing so I am well aware of what Lloyd LJ said in Taylor v Pace Developments Ltd[ [1991] BCC 406 at 408]:
| | |
| |
'There
is only one immutable rule in relation to costs, and that is that there are
no immutable rules.'
|
| | |
I am also
aware of the observations warning against laying down rules for the exercise
of a discretion in relation to costs generally by Bowen LJ in Jones v Curling[
(1884) 13 QBD 262 at 271] and by Brett MR in The Friedeberg[ (1885) 10 PD 112
at 113]. Nevertheless I am fortified by the fact that Lord Goff considered
that such guidance might well become necessary and I believe that the circumstances
of this case indicate the present necessity for guidance. In my judgment,
the following are material considerations to be taken into account, although
I do not suggest that there may not be others which are relevant.
| | |
| (1) |
An
order for the payment of costs by a non-party will always be exceptional:
see the Aiden Shipping case [1986] AC 965 at 980 per Lord Goff. The judge
should treat any application for such an order with considerable caution.
| (2) |
It
will be even more exceptional for an order for the payment of costs to be
made against a non-party, where the applicant has a cause of action against
the non-party and could have joined him as a party to the original proceedings.
Joinder as a party to the proceedings gives the person concerned all the protection
conferred by the rules, e.g. the framing of the issues by pleadings, discovery
of documents, the opportunity to pay into court or to make a Calderbank offer
(see Calderbank v Calderbank[ [1976] Fam 93]), and the knowledge of what the
issues are before giving evidence.
| (3) |
Even
if the applicant can provide a good reason for not joining the non-party against
whom he has a valid cause of action, he should warn the non-party at the earliest
opportunity of the possibility that he may seek to apply for costs against
him. At the very least this will give the non-party an opportunity to apply
to be joined as a party to the action under Ord 15, r 6(2)(b)(i) or (ii).
| | |
Principles
(2) and (3) require no further justification on my part; they are an obvious
application of the basic principles of natural justice.
| (4) |
An
application for payment of costs by a non-party should normally be determined
by the trial judge: see Bahai v Rashidian[ [1985] 1 WLR 1337].
| (5) |
The
fact that the trial judge may in the course of his judgment in the action
have expressed views on the conduct of the non-party neither constitutes bias
nor the appearance of bias. Bias is the antithesis of the proper exercise
of a judicial function: see Bahai v Rashidian[ [1985] 1 WLR 1337 at 1342, 1346].
| (6) |
The
procedure for the determination of costs is a summary procedure, not necessarily
subject to all the rules that would apply in an action. Thus, subject to any
relevant statutory exceptions, judicial findings are inadmissible as evidence
of the facts upon which they were based in proceedings between one of the
parties to the original proceedings and a stranger: see Hollington v F Hewthorn & Co Ltd[ [1943] KB 587] and Cross on Evidence (7th edn, 1990) pp
100–101. Yet in the summary procedure for the determination of the liability
of a solicitor to pay the costs of an action to which he was not a party,
the judge's findings of fact may be admissible: see Brendon v Spiro[ [1938]
1 KB 176 at 192] per Scott LJ, cited with approval by this court in Bahai v Rashidian[ [1985] 1 WLR 1337 at 1343, 1345]. This departure from basic principles
can only be justified if the connection of the non-party with the original
proceedings was so close that he will not suffer any injustice by allowing
this exception to the general rule.
| (7) |
Again
the normal rule is that witnesses in either civil or criminal proceedings
enjoy immunity from any form of civil action in respect of evidence given
during those proceedings. One reason for this immunity is so that witnesses
may give their evidence fearlessly: see Palmer v Durnford Ford (a firm)[ [1992]
QB 483 at 487]. In so far as the evidence of a witness in proceedings may lead
to an application for the costs of those proceedings against him or his company,
it introduces yet another exception to a valuable general principle.
| (8) |
The
fact that an employee, or even a director or the managing director, of a company
gives evidence in an action does not normally mean that the company is taking
part in that action, in so far as that is an allegation relied upon by the
party who applies for an order for costs against a non-party company: see
Gleeson v J Wippell & Co Ltd[ [1977] 1 WLR 510 at 513].
| (9) |
The
judge should be alert to the possibility that an application against a non-party
is motivated by resentment of an inability to obtain an effective order for
costs against a legally aided litigant. The courts are well aware of the financial
difficulties faced by parties who are facing legally aided litigants at first
instance, where the opportunity of a claim against the Legal Aid Board under
s 18 of the Legal Aid Act 1988Acts is very limited. Nevertheless the Civil Legal
Aid (General) Regulations 1989, SI 1989/339, and in particular regs 67, 69
and 70, lay down conditions designed to ensure that there is no abuse of Legal
Aid by a legally assisted person and these are designed to protect the other
party to the litigation as well as the Legal Aid fund. The court will be very
reluctant to infer that solicitors to a legally aided party have failed to
discharge their duties under the regulations—see Orchard v South Eastern Electricity Board[ [1987] QB 565]—and, in my judgment, this principle extends to a reluctance
to infer that any maintenance by a non-party has occurred."
| | | | | | | | |
|
| | |
In Murphy v Young's Brewery[ [1997] 1 WLR 1591] Phillips LJ pointed out that these principles
related largely to questions of procedure. He then said at page 1601:
| | |
| |
"The time
has come to attempt to formulate some principles in the light of these decisions.
My conclusions are as follows.
| | |
| "(1) |
In
Giles v Thompson[ [1994] 1 AC 142 at 164] Lord Mustill suggested that the current
test of maintenance should ask the question whether—
| | |
| |
'there
is wanton and officious intermeddling with the disputes of others in [which]
the meddler has no interest whatever, and where the assistance he renders
to one or the other party is without justification or excuse.'
|
| | |
Where
such a test is satisfied, I would expect the court to be receptive to an application
under s 51 that the meddler pay any costs attributable to his intermeddling.
| (2) |
Where
a non-party has supported an unsuccessful party on terms that place the non-party
under a clear contractual obligation to indemnify the unsuccessful party against
his liability to pay the costs of the successful party, it may well be appropriate
to make an order under s 51 that the non-party pay those costs directly to
the successful party. Such an order may, for instance, save time and costs
in short-circuiting the Third Parties (Rights against Insurers) Act 1930.
Bourne v Colodense[ [1985] ICR 291] is a case where the court might well have
thought fit to make such an order had it appreciated that it had jurisdiction
to do so.
| | (3) |
Where
a trade union funds unsuccessful litigation on behalf of a member the following
factors, in addition to the funding itself, are likely to be present and,
where they are, to make it appropriate to order the union to pay the successful
party's costs should such an order be necessary: (a) an implied obligation
owed by the union to its member to do so—see (2) above; (b) an interest on
the part of the union in supporting and being seen to support the member's
claim; (c) responsibility both for the decision whether the litigation is
to be pursued and for the conduct of the litigation; and (d) expectation based
on convention that the union will bear the costs of the successful party should
the member lose.
| | (4) |
Where
an unsuccessful defendant's costs are funded by insurers who have provided
cover against liability, which is not subject to any relevant limit, the same
considerations that I have set out under (3) are likely to apply."
| |
| | |
I omit
the fifth principle as it is not relevant (and indeed Phillips LJ later said
that none of the considerations of principle were relevant to the facts of
the case). It concerns a decision which was subsequently affirmed but on other
grounds: Chapman Ltd v Christopher[ [1998] 1 WLR 12. At page 1603H] he said:
| |
| |
"Funding
alone will not justify an order against the funder under section 51. I do
not consider that an order under section 51 will normally be appropriate where
a disinterested relative has, out of natural affection, funded costs of a
claim or a defence that is reasonably advanced".
|
| |
| 37. |
In Globe Equities Ltd v Globe Legal Services Ltd[ 5 March 1999, unreported], the Court
of Appeal had to consider what circumstances might justify a order under section
51. Morritt LJ (with whom the other members agreed) said:
| | |
| |
"The
principal argument was directed to the question whether the circumstances
in these applications could properly be regarded as "exceptional". Counsel
for Miller Gardner submitted that they could not. In addition to the judgment
of Balcombe LJ in Symphony Group Plc v Hodgson he referred to similar statements
in Taylor v Pace Developments Ltd[ [1991] BCC 406 at page 410] per Lloyd LJ;
Metalloy Supplies v MA (UK) Ltd[ [1997] 1 WLR 1613 at page 1620] per Millett
LJ, and Murphy v Young & Co's Brewery Plc[ [1997] 1 WLR 1591 at page 1604]
per Phillips LJ. But these statements left open the question by what standard
the circumstances are to be judged in ascertaining whether they are exceptional.
That question was answered by Phillips LJ in TGA Chapman Ltd v Christopher[
[1998] 1 WLR 12 at page 20] where he said:
| | |
| |
"The
test is whether they [sc. the features relied on] are extraordinary in the
context of the entire range of litigation that comes to the courts."
|
I
would also comment that there appears to me to be a danger of treating the
requirement that the circumstances are "exceptional" as being part of the
statute to be applied. It is not. The epithet originates in the first proposition
enunciated by Balcombe LJ in Symphony Group Plc v Hodgson, but it is based
on what Lord Goff said in Aiden Shipping Co Ltd v Interbulk Ltd[ [1986] 1 AC
965, 980]:
| | |
| |
"In
the vast majority of cases it would no doubt be unjust to make an award of
costs against a person who is not a party to the relevant proceedings. But,
as the facts of this case show, that is not always so."
|
| | |
In
none of the cases to which I have referred have "exceptional circumstances"
been elevated into a precondition to the exercise of the power; nor should
they be.
| | |
Ultimately
the test is whether in all the circumstances it is just to exercise the power
conferred by subsections (1) and (3) of s.51 Supreme Court Act 1981Acts to make
a non-party pay the costs of the proceedings. Plainly in the ordinary run
of cases where the party is pursuing or defending the claim for his own benefit
through solicitors acting as such there is not usually any justification for
making someone else pay the costs. But there will be cases where either or
both these tw | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |